Weekly Roadwork Report – TxDOT Atlanta District for Jan. 14-20, 2018

Cass County

None

 

Bowie County

US 259 – At Red River north of De Kalb, constructing new bridge.

US 259 – From US 82 to FM 44, adding shoulders.

FM 1297 – From FM 2878 to FM 559, widening highway.

 

Camp County

None

 

Harrison County

I-20 Westbound – From SH 43 to Gregg County Line, repairing pavement. Various lane closures, expect delays.

I-20 – From FM 31 to 0.5 mile west of US 80, repairing pavement. Various lane closures, expect delays.

FM 1997 – In front of ETBU, adding sidewalk.

FM 2625 – From SH 43 to 0.5 mile west, constructing mine haul road overpass.

US 59 – at SH 43 South (Pinecrest Avenue) in Marshall, repairing concrete pavement.

US 80 – From Loop 281 in Longview to Veterans Avenue, upgrading guard rail.

 

Marion County

None

 

Morris County

None

 

Panola County

SH 149 – At SH 315, constructing overpass and widening highway.

 

Titus County

US 271 – From end of freeway section of US 271 to 0.3 mile south of FM 3417, extending freeway lanes and constructing overpass at FM 3417.

US 271 – At Ripley Creek and Ripley Creek Relief, replacing bridges.

 

Upshur County

SH 155 – From south of Sabine River to US 80, replacing bridges and widening roadway.

SH 155 – From FM 1002 to US 259, upgrading guard rail.

 

Editor’s note: This is a schedule of work being planned for the dates noted above. Weather conditions and unforeseen problems can cause delays or cancelation of work. For more information about construction projects, contact Marcus Sandifer, Public Information Officer, TxDOT Atlanta District, 903-799-1306, marcus.sandifer@txdot.gov.